Tag Archives: ŠKODA AUTO

Center of Samples Testing ŠKODA AUTO opened

In the half of Janury 2021 has ŠKODA AUTO began operating in new highly modern centre for creating testing supporting constructions and prototypes. We are pleased, that we were part of this project.

Study was made by Arch.Design in 2017 by BIM method using Revit software. We were also providing architect’s supervision during following designing and building works. Newly constructed centre has architectonical design connected to current built-up area, created by three other objects.

New production of models and prototypes unites all production steps under one roof, which benefits for ecology as well as production invests. In short distance between teams will be spared 1 800 litre of fuels per year, which equals to five tuns of CO2 emission and the fact, that all storage is attached to car productions it degrees logistic expense as well.

Zdroj: ŠKODA AUTO

Center of Testing Samples ŠKODA AUTO | Arch.Design

Nearby of historical centre of Mladá Boleslav city is finishing building of object of Centre of Testing Samples for which our atelier A3 worked out architectonic study. We provided architect’s supervision during the whole design and building work.

New industrial object is build on place of original warehouses in Mladá Boleslav City close to Česany village, where is placed the oldest part of manufacturing plant of ŠKODA AUTO. Contiguous built-up area is composed of three objects. These objects have similar character as Centre of Testing Samples, but with look and height differences. Designed building compositionaly respects place and orientation of surroundings. Opticaly it is a parted into two parts, due to achieve relief of material of object. Facade of building was designed to opticaly reduce almost seven floors of object. To help enhance optical reduction of building height are there combine vertical windows throught the storeys.

Floors are solved unsually. Height level of main entrance is on level of ground, but first fully valuable floor is situated on the second floor. This solution was choosen due to flood control prevention because of nearby river Jizera.

David Zaplatil